Emergency Maintenance - Pelion UK Cross Site Failover
Scheduled Maintenance Report for Pelion Connectivity Status
Completed
The scheduled maintenance has been completed.
Posted Nov 06, 2024 - 18:30 GMT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 06, 2024 - 17:00 GMT
Scheduled
We will be carrying out essential maintenance on 06/11/2024 between 17:00 and 19:00 UTC.

During this time we will be carrying out a managed failover on one of our cross site links between Pelion's UK data centres. The purpose of this work is to de-risk a supplier change in the upcoming days to minimise any potential for impact to our services.

Location:
UK

Start Date and time:
06/11/2024 17:00 UTC

End Date and time:
06/11/2024 19:00 UTC

Services affected:
Customer IPsecs hosted at our UK data centres may experience a reconnection during the maintenance period

Customer action required:
No customer action is required.
Posted Nov 06, 2024 - 15:53 GMT
This scheduled maintenance affected: Infrastructure (London Datacentre, Manchester Datacentre).