Notification of planned works - US Datacentre Maintenance

Scheduled Maintenance Report for Pelion Connectivity Status

Completed

The scheduled maintenance has been completed.
Posted Jul 09, 2025 - 12:00 BST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 09, 2025 - 08:00 BST

Scheduled

We will be carrying out essential maintenance on 09/07/2025 between 08:00 and 12:00 BST.

During this time we will be bringing up a new cross-site link between our Austin and Las Vegas datacentres.
Telus subscribers may disconnect and reconnect briefly within the maintenance window.

Location:
US

Start Date and time:
09/07/2025 08:00 BST / 02:00 Central

End Date and time:
09/07/2025 12:00 BST / 06:00 Central

Services affected:
Austin and Las Vegas datacentres.
Telus subscribers may disconnect and reconnect briefly within the maintenance window.

Customer action required:
No customer action is required.
Posted Jul 04, 2025 - 15:49 BST
This scheduled maintenance affected: Infrastructure (Austin Datacentre, Las Vegas Datacentre) and Mobile Operators (Telus).