Notification of planned works - Datacentre Maintenance (Change of Date)
Scheduled Maintenance Report for Pelion Connectivity Status
Completed
The scheduled maintenance has been completed.
Posted Jul 22, 2021 - 19:00 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 22, 2021 - 18:01 BST
Scheduled
We will be carrying out essential maintenance on 22/07/2021 between 18:00 and 19:00

During this time we will be performing a routine test of our datacentre cross site link failover.
Customers may notice a small loss of connectivity or a disconnect/reconnect session to their subscribers when we migrate the cross site link. Customers with IPSec might be impacted but should reconnect automatically.
Posted Jul 21, 2021 - 17:16 BST
This scheduled maintenance affected: VPN Technology (London IPSecs, Manchester IPSecs, OpenVPN), Infrastructure (London Datacentre, Manchester Datacentre), and Mobile Operators (Three UK).