Notification of planned works - Datacentre Maintenance (Change of Date)

Scheduled Maintenance Report for Pelion Connectivity Status

Completed

The scheduled maintenance has been completed.
Posted Jul 22, 2021 - 19:00 BST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 22, 2021 - 18:01 BST

Scheduled

We will be carrying out essential maintenance on 22/07/2021 between 18:00 and 19:00

During this time we will be performing a routine test of our datacentre cross site link failover.
Customers may notice a small loss of connectivity or a disconnect/reconnect session to their subscribers when we migrate the cross site link. Customers with IPSec might be impacted but should reconnect automatically.
Posted Jul 21, 2021 - 17:16 BST
This scheduled maintenance affected: Infrastructure (London Datacentre, Manchester Datacentre), VPN Technology (London IPSecs, Manchester IPSecs, OpenVPN), and Mobile Operators (Three UK).