Notification of planned works - Tele2

Scheduled Maintenance Report for Pelion Connectivity Status

Completed

The scheduled maintenance has been completed.
Posted Oct 09, 2025 - 00:30 BST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 07, 2025 - 21:00 BST

Scheduled

Tele2 will be carrying out essential maintenance between 07/10/2025 starting at 21:00 and ending on 09/10/2025 00:30 BST.

During this time Tele2 will be relocating key network infrastructure from their data centers in the USA to Europe.

Start Date and time:
07/10/2025 21:00 BST

End Date and time:
09/10/2025 00:30 BST

Services affected:
Tele2 subscribers registered on the VoLTE bearer will experience a reconnection event during the maintenance period.

Subscribers which are not utilising VoLTE should not be impacted.

Customer action required:
No customer action is required.
Posted Oct 03, 2025 - 14:01 BST
This scheduled maintenance affected: Mobile Operators (Tele2).