Notification of planned works - Austin Data Centre

Scheduled Maintenance Report for Pelion Connectivity Status

Completed

The scheduled maintenance has been completed.
Posted May 13, 2025 - 12:00 BST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 13, 2025 - 08:00 BST

Scheduled

We will be carrying out essential maintenance on 13/05/2025 between 08:00 and 12:00 UTC (02:00 - 06:00 CT)

During this time we will be carrying out essential maintenance to move Radius and platform services between ISPs at our Austin data centre.

Start Date and time:
13/05/2025 08:00 BST (02:00 CT)

End Date and time:
13/05/2025 12:00 BST (06:00 CT)

Services affected:
The Pelion US platform will be unavailable for approximately 10 minutes during the maintenance period.

Telus subscribers creating new sessions are at-risk of disruption at the beginning of the maintenance period. Existing sessions are not impacted.

Customer action required:
No customer action is required.
Posted May 12, 2025 - 17:56 BST
This scheduled maintenance affected: Infrastructure (Austin Datacentre), Pelion (Pelion US Platform), and Mobile Operators (Telus).