Notification of planned works - Manchester Datacentre
Scheduled Maintenance Report for Pelion Connectivity Status
Completed
This maintenance has been rescheduled to begin on 01/12/21
Posted Nov 30, 2021 - 12:27 GMT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 30, 2021 - 11:30 GMT
Scheduled
We will be carrying out essential maintenance on 30/11/2021 between 11:30 and 01/12/2021 20:00.

During this time we will be upgrading some of our internal networking equipment and adding additional capacity in our Manchester DC.
We do not anticipate the upgrades will have any impact on subscriber or customer traffic.

Location: Manchester Datacentre

Start Date and time: 30/11/2021 11:30

End Date and time: 01/12/2021 20:00

Services affected: None.

Customer action required: No customer action is required.
Posted Nov 26, 2021 - 17:20 GMT
This scheduled maintenance affected: Infrastructure (Manchester Datacentre).